Story points measure:
Answer options
A
Hours
B
Complexity/effort relative size
C
Team size
D
LOC
Correct answer: Complexity/effort relative size
Explanation
Points are relative estimates of effort/complexity, not time.
Correct answer: Complexity/effort relative size
Points are relative estimates of effort/complexity, not time.