Choose the missing steps involved in the Change Control Process in the correct order:

Answer options

A
1. Identify and submit change request
B
2. ____________
C
3. Plan the change
D
4. Implement and test the change
E
5. Verify implementation of change
F
6. Close change request
G
Evaluate impacts of change request
H
Review stakeholder feedback
I
Analyze the cost of the proposed change
J
Collect impacts of change request

Correct answer: Evaluate impacts of change request

Explanation

The source marks the correct answer as: Evaluate impacts of change request.