Choose the missing steps involved in the Change Control Process in the correct order: Identify and submit change request ____________ Plan the change Implement and test the change Verify implementation of change Close change request

Answer options

A
Evaluate impacts of change request
B
Bubble Sort
C
Merge Sort
D
Quick Sort

Correct answer: Evaluate impacts of change request

Explanation

The correct answer is: Evaluate impacts of change request.